Toutico, Portugal 2008. Vestas V90 - 3MW
| Project is located in Pampilhosa da'Serra in Portugal. Fair Wind has contracted for 34 units of its V90 -3MW wind turbine. | |
| The works began in October 2008. The project should be completed in autumn of 2009. | ![]() |
| Erection of turbines takes place in nice weather. This is WTG 14A | ![]() |
| Morning on Toutico site. Site is located approximate 700 m above sea level. | ![]() |
| This project is a part of already existing wind turbines farm with enormous numbers of turbines, located on tops of the hills. | |