Place:
 
TOTORAL – CHILE, SOUTH AMERICA
Main Contractor:
 
VESTAS ARGENTINA S.A. – BUENOS AIRES, ARGENTINA
Work:
 
MECHANICAL AND ELECTRICAL ASSEMBLY OF ALL THE ELEMENTS OF THE WIND TURBINES
Type:
 
VESTAS V90 – 2MW
Quantity:
 
23
Starting date:
 
15th May 2009
Duration:
 
6 MONTHS
 
PICTURES
 
 
Together with Vestas we checked, planned and prepared
every part of the installation process before the erection.
 
 
 
 
 
 
Installing the nacelle on a Vestas V90.
 
 
 
 
 
 
Each blade is nearly 45 meters long.
 
 
 
 
 
 
23 new wind turbines have been erected to produce clean and renewable energy.